News

High-speed rail wins legal battle

Sacramento judge rules in rail authority's favor in Peninsula's lawsuit

An effort by Peninsula cities to stop California's high-speed-rail project came to a screeching halt this week when a Sacramento County judge upheld the California High-Speed Rail Authority's environmental-review process for the highly controversial project.

The lawsuit was the second one brought against the Authority by Atherton, Menlo Park and Palo Alto. In the first suit, which prompted the judge to require the rail authority to revise parts of its Environmental Impact Report, Palo Alto filed a "friend of the court" brief in support of the plaintiffs.

The three cities, along with several coalition groups, had argued since 2008 that the rail authority failed to adequately review the Altamont Pass before it chose the Pacheco Pass as its preferred route for the Peninsula segment of the San Francisco-to-Los Angeles line. The cities had challenged the rail authority's ridership projections for the Pacheco segment and argued that the agency did not adequately describe the project in its program-level Environmental Impact Report (which is broader and more general in scope than the project-specific reviews).

Most recently, the cities had argued that the rail authority's environmental analysis is no longer sufficient because of the changing nature of the project. Initially envisioned as a four-track train system, with Caltrain running on the inside tracks along the Peninsula, the project has since morphed (under considerable pressure from Peninsula cities and lawmakers) into a "blended" system in which Caltrain and high-speed rail would share two tracks.

This significant change, the cities contended, means that the original environmental analysis is no longer valid. The original EIR, plaintiffs argued, fails to accurately describe the rail system currently under consideration.

Help sustain the local news you depend on.

Your contribution matters. Become a member today.

Join

Sacramento Superior Court Judge Michael Kenny dismissed this allegation and found that the rail authority had "fully complied" with prior rulings, which required revisions to sections dealing with traffic, noise and vibration impacts associated with narrowing the Monterey Highway to accommodate the new system.

Kenny also argued in his ruling that the rail authority did indeed consider the two-track system, even if its original EIR focused on the four-track one. Kenny specifically cited parts of the EIR that dealt with "phased implementation" of the system and the "blended system concept." The rail authority had previously considered the "blended system" as an interim step while the state proceeds with a four-track system.

The discussion of the blended alternative in the EIR, Kenny wrote, was sufficient even if the document does not explicitly set forth this alternative as the finished product.

"Specifically, the discussion of the phased or blended system disclosed to the public, and to the decision-makers, what the changed effects of such a system would be," Kenny wrote, referring to the blended system. "That disclosure served the information purposes of CEQA (California Environmental Quality Act) whether the blended system in the Caltrain corridor is an interim step toward final construction or whether, as petitioners contend, it may be the final end point for construction."

He also rejected the cities' contention that the new emphasis on the blended approach should require the rail authority to recirculate its EIR, triggering a fresh public-review process.

Stay informed

Get daily headlines sent straight to your inbox in our Express newsletter.

Stay informed

Get daily headlines sent straight to your inbox in our Express newsletter.

The environmental report's discussion of phasing and implementation of the blended system, Kenny wrote, "served the goal of meaningful public participation in the CEQA review process."

The rail authority, Kenny wrote, "adequately disclosed to the public how the project would be implemented and described in adequate detail what the environmental consequences of such implementation would be."

"Even if the process was not absolutely perfect, it was sufficient to comply with CEQA," Kenny wrote.

Even though the Peninsula cities' arguments didn't carry the day, Kenny's ruling could be a mixed blessing for the municipalities. The rail bill approved by the state Senate last fall allocated $1.1 billion for long-awaited improvements to the Caltrain corridor. This will include $700 million for electrification of the popular but cash-strapped system – a project that the agency has been studying for more than a decade. The funding may have been in jeopardy had the lawsuit gone the cities' way.

Last week, state Sen. Jerry Hill, D-San Mateo, proposed a bill that would further lock in the funds for Caltrain.

Most Viewed Stories

Most Viewed Stories

Kenny's ruling is the latest of several notable victories for the once-beleaguered rail authority. Last year, the state Senate approved by a single vote funding for the first segment of the rail line, which would be constructed in the Central Valley. Kenny's ruling in favor of the authority allows the rail project to bypass another potential delay.

Rail authority CEO Jeff Morales celebrated the legal victory with a statement that called Kenny's ruling a "testament to the fact that the Authority is committed to delivering the high-speed rail project in accordance with the law and in partnership with the public."

"We continue to move forward to start

construction this summer and create thousands of jobs in California," Morales wrote.

Stuart Flashman, the attorney for the Peninsula cities, said the city officials will now have to consider whether to appeal the ruling. Flashman said his clients continue to distrust the rail authority and its assurances about the blended system.

Even if they choose not to pursue this matter further, the rail authority still has to clear other hurdles. Flashman said he is still waiting on a ruling on an appeal of an earlier lawsuit from the Peninsula cities -- an appeal that criticizes the rail authority's ridership projections. And another lawsuit, filed by Menlo Park attorney Michael Brady, claims that the rail project is not consistent with the one the voters approved in 2008, when they supported a $9.95 billion bond for a high-speed rail system. Proposition 1A had pegged the cost of the system at about $33 billion and specified that the trains should be able to get from San Francisco to Los Angeles in less than 2 hours and 40 minutes.

"I don't think either the funding or the timing requirements can be met with the blended system," said Flashman, who is working with Brady on the lawsuit. "There hasn't been a detailed analysis. The authority claims that it can meet the requirements but when pressed on documents, it doesn't have any."

Craving a new voice in Peninsula dining?

Sign up for the Peninsula Foodist newsletter.

Sign up now
Gennady Sheyner
 
Gennady Sheyner covers the City Hall beat in Palo Alto as well as regional politics, with a special focus on housing and transportation. Before joining the Palo Alto Weekly/PaloAltoOnline.com in 2008, he covered breaking news and local politics for the Waterbury Republican-American, a daily newspaper in Connecticut. Read more >>

Follow on Twitter @paloaltoweekly, Facebook and on Instagram @paloaltoonline for breaking news, local events, photos, videos and more.

High-speed rail wins legal battle

Sacramento judge rules in rail authority's favor in Peninsula's lawsuit

An effort by Peninsula cities to stop California's high-speed-rail project came to a screeching halt this week when a Sacramento County judge upheld the California High-Speed Rail Authority's environmental-review process for the highly controversial project.

The lawsuit was the second one brought against the Authority by Atherton, Menlo Park and Palo Alto. In the first suit, which prompted the judge to require the rail authority to revise parts of its Environmental Impact Report, Palo Alto filed a "friend of the court" brief in support of the plaintiffs.

The three cities, along with several coalition groups, had argued since 2008 that the rail authority failed to adequately review the Altamont Pass before it chose the Pacheco Pass as its preferred route for the Peninsula segment of the San Francisco-to-Los Angeles line. The cities had challenged the rail authority's ridership projections for the Pacheco segment and argued that the agency did not adequately describe the project in its program-level Environmental Impact Report (which is broader and more general in scope than the project-specific reviews).

Most recently, the cities had argued that the rail authority's environmental analysis is no longer sufficient because of the changing nature of the project. Initially envisioned as a four-track train system, with Caltrain running on the inside tracks along the Peninsula, the project has since morphed (under considerable pressure from Peninsula cities and lawmakers) into a "blended" system in which Caltrain and high-speed rail would share two tracks.

This significant change, the cities contended, means that the original environmental analysis is no longer valid. The original EIR, plaintiffs argued, fails to accurately describe the rail system currently under consideration.

Sacramento Superior Court Judge Michael Kenny dismissed this allegation and found that the rail authority had "fully complied" with prior rulings, which required revisions to sections dealing with traffic, noise and vibration impacts associated with narrowing the Monterey Highway to accommodate the new system.

Kenny also argued in his ruling that the rail authority did indeed consider the two-track system, even if its original EIR focused on the four-track one. Kenny specifically cited parts of the EIR that dealt with "phased implementation" of the system and the "blended system concept." The rail authority had previously considered the "blended system" as an interim step while the state proceeds with a four-track system.

The discussion of the blended alternative in the EIR, Kenny wrote, was sufficient even if the document does not explicitly set forth this alternative as the finished product.

"Specifically, the discussion of the phased or blended system disclosed to the public, and to the decision-makers, what the changed effects of such a system would be," Kenny wrote, referring to the blended system. "That disclosure served the information purposes of CEQA (California Environmental Quality Act) whether the blended system in the Caltrain corridor is an interim step toward final construction or whether, as petitioners contend, it may be the final end point for construction."

He also rejected the cities' contention that the new emphasis on the blended approach should require the rail authority to recirculate its EIR, triggering a fresh public-review process.

The environmental report's discussion of phasing and implementation of the blended system, Kenny wrote, "served the goal of meaningful public participation in the CEQA review process."

The rail authority, Kenny wrote, "adequately disclosed to the public how the project would be implemented and described in adequate detail what the environmental consequences of such implementation would be."

"Even if the process was not absolutely perfect, it was sufficient to comply with CEQA," Kenny wrote.

Even though the Peninsula cities' arguments didn't carry the day, Kenny's ruling could be a mixed blessing for the municipalities. The rail bill approved by the state Senate last fall allocated $1.1 billion for long-awaited improvements to the Caltrain corridor. This will include $700 million for electrification of the popular but cash-strapped system – a project that the agency has been studying for more than a decade. The funding may have been in jeopardy had the lawsuit gone the cities' way.

Last week, state Sen. Jerry Hill, D-San Mateo, proposed a bill that would further lock in the funds for Caltrain.

Kenny's ruling is the latest of several notable victories for the once-beleaguered rail authority. Last year, the state Senate approved by a single vote funding for the first segment of the rail line, which would be constructed in the Central Valley. Kenny's ruling in favor of the authority allows the rail project to bypass another potential delay.

Rail authority CEO Jeff Morales celebrated the legal victory with a statement that called Kenny's ruling a "testament to the fact that the Authority is committed to delivering the high-speed rail project in accordance with the law and in partnership with the public."

"We continue to move forward to start

construction this summer and create thousands of jobs in California," Morales wrote.

Stuart Flashman, the attorney for the Peninsula cities, said the city officials will now have to consider whether to appeal the ruling. Flashman said his clients continue to distrust the rail authority and its assurances about the blended system.

Even if they choose not to pursue this matter further, the rail authority still has to clear other hurdles. Flashman said he is still waiting on a ruling on an appeal of an earlier lawsuit from the Peninsula cities -- an appeal that criticizes the rail authority's ridership projections. And another lawsuit, filed by Menlo Park attorney Michael Brady, claims that the rail project is not consistent with the one the voters approved in 2008, when they supported a $9.95 billion bond for a high-speed rail system. Proposition 1A had pegged the cost of the system at about $33 billion and specified that the trains should be able to get from San Francisco to Los Angeles in less than 2 hours and 40 minutes.

"I don't think either the funding or the timing requirements can be met with the blended system," said Flashman, who is working with Brady on the lawsuit. "There hasn't been a detailed analysis. The authority claims that it can meet the requirements but when pressed on documents, it doesn't have any."

Comments

Herb Borock
Professorville
on Mar 1, 2013 at 10:26 am
Herb Borock, Professorville
on Mar 1, 2013 at 10:26 am

The writs previously issued by Judge Kenny required the High Speed Rail Authority to revise specified parts of its enviromental review of the project.

The Peninsula cities "do not contend that respondent failed to comply with the writs with regard to any of the areas of deficiency the Court identified in its earlier rulings".

Instead, the cities argued that the enviromental review should have analyzed the two-track blended system, because Caltrain had written that it would not approve a four-track system.

Here is what Judge Kenny said about that argument:

"The Court notes that petitioners appear to treat the Peninsula Corridor Joint Powers Board's refusal to consider construction of the four-track system to be inherently irreversible and thus absolutely to preclude construction of a four-track system in the Caltrain right of way forever. While it is clear that the Board opposes the four-track system now, it is not necessarily clear that this will always be the case. The Court observes that the Board is an appointed body, the members of which are appointed from various governmental entities and locations. It is not inconceivable that its position on construction of the high speed rail system, which is essentially a political decision, could change in the future."

The judge's statement about Caltrain also applies to the Palo Alto City Council, which has already changed its position once from supporting the ballot measure for high speed rail to opposing the current four-track plan.

The City Council's current position is essentially a political decision that needs to be supported, because there continue to be people in Palo Alto and elswhere that want the Council to change its position again.


resident
Downtown North
on Mar 1, 2013 at 10:30 am
resident, Downtown North
on Mar 1, 2013 at 10:30 am

Years of lawsuits and delays have just wasted tax payer money and driven up the price, which will also have to be paid by the tax payers. If the NIMBYs had just listed to the voters in the first place, this project would have gone much more smoothly and cheaply. Blame the NIMBYs for your higher taxes.


Michael Tompert
Crescent Park
on Mar 1, 2013 at 11:24 am
Michael Tompert, Crescent Park
on Mar 1, 2013 at 11:24 am

Hurray! A small step for the high speed rail authority, but a giant step forward for Palo Alto and California towards joining the rest of the developed world in building sustainable and forward looking transportation.


Mel
Atherton
on Mar 1, 2013 at 12:25 pm
Mel, Atherton
on Mar 1, 2013 at 12:25 pm

What a bunch of wasted consultancy money these cities are dumping needlessly away. We could supplement more police and firefighters programs with these funds. Learn to work together as a team to solve infrastructure problems like the High Speed Rail Designs.

On the internet, you can view the 'Railroader' Menlo Park Station Closing Scene clip that illustrates the frustration on commuters waiting for this construction to begin. Railroader is a documentary style movie that is located at the following hotlink:

Web Link

Regards,

Mel


Leonard
Old Palo Alto
on Mar 1, 2013 at 12:40 pm
Leonard, Old Palo Alto
on Mar 1, 2013 at 12:40 pm

Yes! Let the building begin...and yes I will use this transportion! Can't wait!


Pro HSR
Adobe-Meadow
on Mar 1, 2013 at 1:13 pm
Pro HSR, Adobe-Meadow
on Mar 1, 2013 at 1:13 pm

Stop suing and attacking, start working WITH the project, and make it the best possible. HSR goes through nice suburban neighborhoods and into downtown capital cities all over Europe, and it's not a problem.

Let's just work to get the best layout we possibly can through cooperation. And it needs to stop in PA for us to fully benefit from it!


Pro HSR
Adobe-Meadow
on Mar 1, 2013 at 1:13 pm
Pro HSR, Adobe-Meadow
on Mar 1, 2013 at 1:13 pm

Stop suing and attacking, start working WITH the project, and make it the best possible. HSR goes through nice suburban neighborhoods and into downtown capital cities all over Europe, and it's not a problem.

Let's just work to get the best layout we possibly can through cooperation. And it needs to stop in PA for us to fully benefit from it!


Resident
Another Palo Alto neighborhood
on Mar 1, 2013 at 1:15 pm
Resident, Another Palo Alto neighborhood
on Mar 1, 2013 at 1:15 pm

HSR must start working with Caltrain not the two working independently.

Work together with the other Bay Area transit agencies also.


Resident
Menlo Park
on Mar 1, 2013 at 5:11 pm
Resident, Menlo Park
on Mar 1, 2013 at 5:11 pm

Hilarious that additional environmental review would stall a project destined to get many cars off the road.

I'm fairly new to this particular issues, so feel free to point me to any discussion if it's come up before, but what is the benefit to sharing the tracks? quicker construction? ability to electrify Caltrain using funds marked for HSR? less upset of land and infrastructure already in place?

Seems to me that HSR and Caltrain sharing tracks is only buying some time that will be way repaid in delays when both systems are up and running. Please enlighten me.


Craig Laughton
College Terrace
on Mar 1, 2013 at 5:54 pm
Craig Laughton, College Terrace
on Mar 1, 2013 at 5:54 pm

I think that HSR does not pencil, at several levels. In fact, I think it is an absurd waste of resoruces, time and money. However, Barack Obama was reelected and Jerry Brown is our Guv. Our city council unanimously endorsed this turkey. Stupid is as stupid does.

HSR will go through Palo Alto as a four-track elevated system, as originally proposed.


Laurel
Adobe-Meadow
on Mar 1, 2013 at 9:27 pm
Laurel, Adobe-Meadow
on Mar 1, 2013 at 9:27 pm

wow, the HSR shills are out today! This thing was, and continues to be a fraud, nothing more. A well executed siphoning of tax dollars from the public, to the big labor unions who helped Jerry get re-elected, nothing more. The train is the cod-piece over the bulging politically motivated boondoggle.

HSR shills, did you know that the CA HSR claims that they will have 117 Million riders by 2030? Amtrak, with a record year, had 31.2 million rider for their nation wide network, a 3.2% increase over last year. hmm, if that grown continues until 2030, they might have a few million riders by 2030, but miraculously, CA HSR will have nearly 4 times Amtrack's nation wide ridership? Really.

And how about that cost, officially only $69B. Most likely hundreds of billions of your tax dollars after principal, interest, and insider waste kick in. Where's that coming from?

A real waste.


TheTruth
another community
on Mar 2, 2013 at 9:03 am
TheTruth, another community
on Mar 2, 2013 at 9:03 am

GOOD...The Nimbys and the grandstand sideshow of "terror" tales has been thrown out..now an new upgraded Caltrain and HSR will move forward..Next we need to get rid of the Rebubs/teabaggers in DC so funding can move forward


BostonBigDig
Community Center
on Mar 2, 2013 at 6:45 pm
BostonBigDig, Community Center
on Mar 2, 2013 at 6:45 pm

Hey TheTruth, Who is going to pay for the grand swindle? You? Please elaborate. What gets cut to pay for the train to nowhere?


Crescent Park Dad
Crescent Park
on Mar 5, 2013 at 10:18 pm
Crescent Park Dad, Crescent Park
on Mar 5, 2013 at 10:18 pm

Pro HSR: Where do you propose to build the required 3000 car garage for your PA HSR stop and who is going to pay for it (HSR will not)? And what residential street do you plan to take over to facilitate moving the HSR station car traffic from 101 to downtown?


Don't miss out on the discussion!
Sign up to be notified of new comments on this topic.

Post a comment

On Wednesday, we'll be launching a new website. To prepare and make sure all our content is available on the new platform, commenting on stories and in TownSquare has been disabled. When the new site is online, past comments will be available to be seen and we'll reinstate the ability to comment. We appreciate your patience while we make this transition.