Caltrain's plan to electrify its trains is about to roll through Palo Alto, where crews are preparing to install nearly 200 poles along the railroad tracks.
The agency is now in the midst of electrifying the 51-mile stretch between San Francisco and San Jose, a project that will allow Caltrain to increase its service from five to six trains per hour in each direction during peak commute hours. The project began in 2017 in San Mateo County and in San Jose and is now entering its next phases in San Francisco and north Santa Clara County.
The project involves installing 3,000 poles throughout the 51-mile segment to support the overhead wires that will power the system. This includes 196 poles in Palo Alto, Caltrain's Public Involvement Manager Greg Parks said Tuesday night during a community meeting on the project at Rinconada Library. The poles will range in height from 30 feet to 50 feet and they will be spaced about 180 feet apart.
To date, the agency's contractors have been pruning trees and installing foundation, which entails excavating soil and placing rebar into the ground. In February, Caltrain will start installing poles and wires. The work is expected to be completed this fall.
Later this year, Caltrain plans to build a paralleling station on agency-owned property adjacent to 195 Page Mill Road, about a block south of Oregon Expressway. The unmanned station will include two box-like structures (a transformer and a control house) and two 50-foot-tall gantries, which are steel structures that support wires that connect to the overhead contact system and power the trains. According to the agency, one gantry will be installed near the transformer, while the other would go up on the other side of the tracks.
The paralleling station is needed to maintain and regulate the power to the electrified train system, ensuring that the current is running at 25 kilovolts, Parks said. It is one of seven stations that are being installed as part of the project. Caltrain plans to add vegetation and possibly plant trees to screen the equipment.
Work on the electrification project will take place day and night, with occasional 24-hour work on the weekends, according to a handout provided at the meeting. The agency plans to use acoustical noise blankets and position lights away from homes and businesses to minimize impact, according to staff.
Staff also indicated at the meeting that the project would likely require a lane closure at Alma Street.
Several residents asked at the meeting about the impact of Caltrain's electrification project on Palo Alto's ongoing effort to achieve grade separation, the redesign of the rail crossings so that train tracks and roads would not intersect. That project is driven by expectations that Caltrain will continue to expand its service, creating massive backups at rail crossings as gate-down times increase.
Parks said Caltrain is working closely with the city of Palo Alto and other cities that are pursuing grade separation. The agencies are sharing plans and cities are aware of Caltrain's plans to build the overhead system, which has been in the works for three years.
"As you know, Palo Alto is in the planning phase of what they're going to do with grade crossings and we're not touching the grade crossing or separating grade crossings as part of this project," Parks said.
Casey Fromson, Caltrain's director of communication and government affairs, also assured residents that the project would not preclude cities up and down the corridor from pursuing their plans for grade separation.
In Palo Alto, where the City Council has a goal of choosing its preferred alternative for grade separation by this spring, the actual construction isn't expected to be completed until 2030. Fromson noted that if Caltrain were to wait for all the cities to complete their grade separation projects, it would never be able to move ahead with electrification. She also indicated that Caltrain would be able to relocate its equipment to accommodate future designs.
"Moving poles and wires, as you see, is not a ton of work," Fromson said. "It's not ideal, but it wouldn't be the end of the world."
View Caltrain's fact sheet on the upcoming electrification work in Palo Alto, including a timeline of construction activities, here.
Comments
Duveneck/St. Francis
on Jan 29, 2020 at 9:52 am
on Jan 29, 2020 at 9:52 am
We need better public transportation on the peninsula. Caltrain is standing-room-only during commute hours, which is really difficult for people who aren't strong and fit. Limited capacity is pushing more people into private cars, causing traffic jams and traffic collisions and increased air pollution all over town. The sooner they can fix Caltrain, the better.
Adobe-Meadow
on Jan 29, 2020 at 10:47 am
on Jan 29, 2020 at 10:47 am
Please note that the lane closure on Alma is temporary and only for construction vehicle access to the tracks. It's for as long as several weeks, not permanent.
Mountain View
on Jan 29, 2020 at 10:52 am
on Jan 29, 2020 at 10:52 am
Great we're moving to electric power but (BUT) the current state of the rain cars and track is pretty miserable.
Alas, I'm spoiled. I've ridden trains in Europe which show how well a rail system CAN be run.
I also just returned from New Mexico taking the Rail Runner from Albuquerque to Santa Fe. Smooth. Fast. Comfortable. All three things that Caltrain is not (at the moment).
Time to replace wheel bearings, ensure the track is smooth and upgrade the cars along WITH the engines as Caltrain moves into the future . . . with electricity.
Midtown
on Jan 29, 2020 at 11:01 am
on Jan 29, 2020 at 11:01 am
@James Thurber: All of that is already coming. All of the Caltrain train sets are being replaced with electric train sets. A few of the existing train sets will be saved so that service between SJ and Gilroy can still run.
Adobe-Meadow
on Jan 29, 2020 at 11:32 am
on Jan 29, 2020 at 11:32 am
@ George
Only about 75% of the Caltrain train sets will be new. That means we will still have the diesel train sets operating beyond those going to Gilroy. The oldest train sets will be retired, however.
Downtown North
on Jan 29, 2020 at 4:29 pm
on Jan 29, 2020 at 4:29 pm
"a project that will allow Caltrain to increase its service from five to six trains per hour in each direction during peak commute hours."
All that fuss and money for only 20% service increase, and only in rush hour? Come on. Buy some real diesels and you're there.
Another Palo Alto neighborhood
on Jan 29, 2020 at 6:56 pm
on Jan 29, 2020 at 6:56 pm
Have to agree with Curmudgeon. 20% is not much bang for the buck.
Well, unless you are Caltrain and its not your buck, or you are a real-estate developer and Caltrain's increased capacity gets you out of having to provide adequate parking in your next project. Then it a great deal.
another community
on Jan 29, 2020 at 7:20 pm
on Jan 29, 2020 at 7:20 pm
Good for the environment, but the electric wires don't look so nice.
Just look at Portland or Tokyo.
I guess this is what the Bay Area has turned into - another over populated ugly dense city.
The original rail line was never intended to handle high speed trains.
When I was a kid, I had to cross those tracks to go to school every day - no suicides. The train went so slow between the stations that kids could be on the track and always get out of the way in time. Not now!
How about re-routing those tracks to run down Bay Shore freeway?
It would move the noise and congestion to the periphery of the city, instead of being in the center of the city, and near our school. Things would be much better.
Downtown North
on Jan 31, 2020 at 6:52 am
on Jan 31, 2020 at 6:52 am
Glad this is finally happening. I don’t like the 20% capacity increase but, I would like to see two additional benefits: shorter trip time (electric trains can accelerate faster, give back energy when decelerating) and every train stops at every station even with a shorter trip time. Heard about this in the past but not in this article.
Note that electric trains are quieter, and with eventual elimination of grade crossings much fewer horns will be needed.
Trains need to go through center of town — otherwise commuters need taxis to go downtown. Makes no sense.
Portola Valley
on Jan 31, 2020 at 10:16 pm
on Jan 31, 2020 at 10:16 pm
Can’t wait for Gavin’s super train whisking valley commuters past PA at 200 mph! Maybe I’ll buy some rentals cheap along the ROW