Palo Alto's effort to redesign its rail corridor received a boost over the summer when the city received more than $30 million in grants — a gift that could add some urgency to the complex project.
According to Chief Transportation Official Philip Kamhi, the city learned in June that the Federal Railroad Administration has allocated $6 million for development of alternatives to separate the roadways from the train tracks at three crossings: Churchill Avenue, Meadow Drive and Charleston Road.
The following month, the city was notified that it had received a $23.8 million grant from the California State Transportation Agency (CalSTA) for the final design phase of the Churchill grade separation.
Under normal conditions, the windfall would be a cause for celebration rather than anxiety. There's been nothing normal, however, about Palo Alto's effort to develop rail redesign alternatives.
The project launched more than a decade ago and has featured three separate stakeholder committees, dozens of public hearings and a gradual winnowing down of more than three dozen alternatives into the five currently on the table.
It's been, in short, slow going.
The federal money may force it to pick up the pace. Kamhi said Wednesday, Aug. 23, that both grants come with deadlines. The FRA grant required the city to begin the engineering and environmental work on the three rail crossings in July, a timeline that was guided by the application that the city submitted nearly a year-and-a-half ago.
The city's timeline, however, has changed since then as citizens pitched new designs and council members commissioned additional studies, including ones focusing on things like geotechnical conditions and sea-level rise.
Palo Alto has also entered into an agreement with Caltrain under which the transit agency will review the city's grade-separation alternatives for feasibility and for compatibility with its own plans for four-track segments. That review, all council members agree, is necessary, but it will necessarily add time to the process of choosing alternatives.
Time may be in short supply. Kamhi said that for the city to meet its obligations, it would have to choose its preferred alternatives by April 2024. Even that would require the FRA to agree to a deadline extension, according to Kamhi.
In discussing the grants, members of the city's Rail Committee acknowledged that their winnings put them in a bit of a bind.
Members fretted about a potential scenario in which the city accepts the money but is unable to complete the plans by the deadline. In that case, it would not get reimbursed by the federal and state agency.
"We actually need to deliver in order to get reimbursed," Kamhi said. "If we get off the track and we don't deliver the project, potentially we're on the hook for the money."
Refusing the grant money isn't a great option either. Kamhi suggested that agencies don't look kindly on cities that apply for grants and then, after months had been spent on these applications, decline the funding.
"That said, it's a lot better than if we started to try to deliver the project and then fail," he said. "Then we really look bad, we don't get reimbursement and they take our funding and have to reallocate it to another project later on."
Council member Vicki Veenker referred to the prospect of losing the money and ending up with an unfinished product as a "double whammy."
"We're in this usual situation where we have this great news about getting these grants and we may have an inability to use them in a way that is good in the long run and avoids the double whammy effect," Veenker said,
Others shared her ambivalence. The council had already determined that its biggest priority is the two southernmost crossings — Meadow and Charleston — which are being evaluated in tandem.
But because the CalSTA grant is specifically for the Churchill crossing, the city would have to now prioritize design work for that crossing. Committee Chair Pat Burt argued that this is an important community decision, particularly given the fact that north Palo Alto already has several grade crossings while south Palo Alto has none.
"As of right now, it seems like what they want to do is to have us continue, pedal-to-the-metal and make as much progress as we can on moving forward both of these alternatives," Burt said. "The question is: Are we in any way boxing ourselves in by accepting the Churchill dollars?"
So far, the council has narrowed down its options for Meadow and Charleston to a trench, an underpass and a "hybrid" that includes raised tracks and lowered roads.
On Churchill, the council's preferred alternative is an underpass that lowers Churchill under the tracks and allows cars to turn on Alma Street. Its backup option if this one fails is closure of Churchill to cars.
Committee members noted at the Wednesday discussion that the grade separation project has — at least in one respect — become less urgent. For years, council members were worried about Caltrain sharply ramping up its service and creating massive congestion at the rail crossings because of the additional gate time.
The pandemic, which sharply reduced transit ridership, changed the calculus. Burt, who serves on the boards of directors at both Caltrain and the Santa Clara Valley Transportation Authority, said transit agencies all over the state are revising their ridership models.
"When Caltrain got federal dollars, they had to submit a service model to the feds based on six trains per hour. They're now needing to go back to feds to renegotiate that because they don't have the demand for that. And they're not alone — this is transit agencies all facing similar things," Burt said.
Council member Ed Lauing suggested that the grant need not change the council's message to the community. The council, he noted, remains committed to grade separation at all three crossings. The only thing that may change is the prioritization of preliminary work.
Lauing called the council's grant-instigated conundrum the "ultimate irony."
"It's not as urgent anymore relative to the pandemic and so on, and yet it's more urgent for us to pick the alternatives," Lauing said.
Comments
Registered user
College Terrace
on Aug 23, 2023 at 10:20 pm
Registered user
on Aug 23, 2023 at 10:20 pm
So let’s count the ways in which our city turns away grant & federal dollars while appeasing it’s high end SFHOwners. Delaying track train plans because of sea level rise? Uh wait. CC overwhelmingly votes in favor of what? 4000 homes on the bay shore, transitional housing units on the Bay Shore and two waste water plants on the Bay Shore — where the water will lap like Fukushima meltdown in a flood, quake. Yet cannot decide on track grade design 1 1/2 miles from said Bay Shore because of Sea Level rise??? What a ironic farce. Throwing down the toilet once again good money for bad leadership and private interests !
Registered user
Crescent Park
on Aug 24, 2023 at 9:04 am
Registered user
on Aug 24, 2023 at 9:04 am
Isn't it telling that the CC gets awarded grants (Hooray!) and the first reaction is "oh no. now we need to actually execute. this isn't going to go well." How embarrassing.
Grade separation is a good thing. Its necessary. A temporary change in traffic patterns is exactly that, temporary.
Registered user
Another Palo Alto neighborhood
on Aug 24, 2023 at 9:55 am
Registered user
on Aug 24, 2023 at 9:55 am
Does the City and School District talk to each other?
In fact, does the writer of this article talk to the writer of the article about the new bike path on Churchill?
Is Churchill now being thought of as a bike blvd?
Registered user
Adobe-Meadow
on Aug 24, 2023 at 9:56 am
Registered user
on Aug 24, 2023 at 9:56 am
Traffic patterns in this city are happening every day. Charleston has been changed, now San Antonio is overloaded. !01 has been changed - did they all think that rush hour traffic would go away? Oregon at rush hour is fully filled up. If you add more people then you add more traffic - people cannot live here for free - they have to go to work.
I saw them building a loop under the ECR / tracks up in San Bruno area. They supported the construction with RR ties and got is done in record time. But the "tunnel" is for autos and small trucks only - no big buses or big trucks - there is a height limitation. This can be done fairly quickly - San Mateo County appears to move out fast and get good results.
To be fair Caltrain in San Mateo County is on an elevated piece of land with parking at street level. RWC is at street level. Each city has a different elevation of the tracks so no one solution for all.
Registered user
South of Midtown
on Aug 24, 2023 at 10:08 am
Registered user
on Aug 24, 2023 at 10:08 am
The major obstacle to implementing grade separations in South Palo Alto is not Palo Alto but Caltrain. They have not been willing to commit to two tracks in South Palo Alto even though all current plans are for two tracks. They prefer grade separations designed for four tracks which could double the cost and require far more property acquisitions. That would provoke much more opposition from those losing their homes with little ability to find replacement homes in Palo Alto. Eminent domain seizures would increase costs and time of construction dramatically. If Caltrain would only commit permanently to their own 20 yearly plans, grade separations would be quickly approved and constructed. This is all dependent on Caltrain’s agreement to review plans for feasibility and compatibility with their own plans. Will they use their existing plans or insist that Palo Alto grade crossings accommodate some far future plan of four tracks in south Palo Alto that is highly unlikely to happen due to the financial cost and local opposition to Caltrain’s need to seize housing and/or two to three lanes of Alma to implement four tracks? Caltrain right of way shrinks to 60 feet around E. Meadow. Four tracks require a minimum of 100 ft plus more for construction.
Registered user
another community
on Aug 24, 2023 at 10:27 am
Registered user
on Aug 24, 2023 at 10:27 am
Having moved to Half Moon Bay in June of this year I'm enjoying a cooler climate but missing the sounds of train whistles and the occasional rattle of those steel wheels on the tracks.
I've suggested before that the least expensive way to "solve" these railroad / automobile interchanges is with concrete barricades. They're cheap and there are a lot of old ones around. You could install them in a morning and voila, all issues are solved. (PS: Leave a small space for students and bicycles to pass by).
Registered user
Green Acres
on Aug 24, 2023 at 10:31 am
Registered user
on Aug 24, 2023 at 10:31 am
As alluded to near the end of the story, there will not be an increase in number of trains in the foreseeable future. Since the current crossings are working fine, it seems the least disruptive and cheapest option is to put off grade separation for at least another decade or two.
Registered user
Professorville
on Aug 24, 2023 at 11:02 am
Registered user
on Aug 24, 2023 at 11:02 am
Only 9 months to make a decision that has been contemplated for a decade? Preposterous!
Registered user
Menlo Park
on Aug 24, 2023 at 11:08 am
Registered user
on Aug 24, 2023 at 11:08 am
The continued existence of at-grade crossings of a busy railroad in the 21st century is unacceptable. San Carlos and Belmont did it years ago. Palo Alto can, too. Just do it! Hey, Menlo Park. Pay attention! The problems and challenges are the same.
Registered user
Old Palo Alto
on Aug 24, 2023 at 11:12 am
Registered user
on Aug 24, 2023 at 11:12 am
A gift that could add some urgency to the project!!!!! I do not think the city understands what urgency means or possibly it means within a given century or two. Dither Dither Dither.
Registered user
Duveneck/St. Francis
on Aug 24, 2023 at 2:16 pm
Registered user
on Aug 24, 2023 at 2:16 pm
Sunnyvale is in motion with a Caltrain grade separation project: I happened to see it in the city’s newsletter sent to residents. If I can locate an online reference, I’ll post it. They’re taking ACTION.
Registered user
College Terrace
on Aug 26, 2023 at 2:46 am
Registered user
on Aug 26, 2023 at 2:46 am
@Stayinhome nailed it. If this was about the freeway going through Oakland in 1952, no problem. Losing six houses on a train corridor in PA for climate friendly trains is akin to the Oppenheimer’s Atom Bomb? Oregon expressway took out multitudes of PA houses. What’s left? A quaint outdated, ghostly sign saying “California Street Shopping District” and a gazillion Tesla’s limping by.
Registered user
Barron Park
on Aug 26, 2023 at 9:44 am
Registered user
on Aug 26, 2023 at 9:44 am
While the city manager runs city operations it is the responsibility of the council to set policy. Can't the council vote to take the money and then direct the city manager - in clear and unambiguous language - to make the completion of the needed work his staff's highest priority?
Oh. Wait. That would mean other projects might be delayed and some group or another might get upset and we can't have that can we.
Registered user
Barron Park
on Aug 26, 2023 at 10:18 am
Registered user
on Aug 26, 2023 at 10:18 am
Marie lays it out nicely in her post. As I read matters, until Caltrain makes clear that HSR will not be pushed through the Peninsula, thus relieving Palo Alto of the burden of choosing a locally preferred option that would not *exclude* a 4-track configuration at some future time to accommodate the vanishingly likely possibility that HSR will terminate in downtown San Francisco, this city will be artificially limited in its choice of grade crossing options.
Registered user
Old Palo Alto
on Aug 29, 2023 at 10:56 am
Registered user
on Aug 29, 2023 at 10:56 am
Caltrain/HSR requires that no grade separation solution may preclude four tracks on the ROW. That ship has sailed, so what's left for Caltrain to decide?
The ROW is wide enough for four tracks in some places and too narrow in others. Caltrain cannot exceed the existing boundaries of the ROW without acquiring land from CPA. Caltrain wants two additional passing tracks somewhere on the ROW. They need to pick a track configuration where the ROW is wide enough for the additional tracks. Again, this needs to be within the existing ROW boundaries. No further decision making by Caltrain is needed.
How CPA implements grade separation is up to the city. CPA has been chasing its tail on this for 10+ years with no viable solution to show for it, despite engaging three different engineering firms, holding countless community-outreach meetings and appointing several rail committees to study the matter. That we haven't got a workable plan after lo this many years is due to CPA's indecision, not Caltrain's or CA HSR's.
Registered user
College Terrace
on Aug 29, 2023 at 1:37 pm
Registered user
on Aug 29, 2023 at 1:37 pm
I am not understanding why the City applied for time-sensitive grants, knowing the decisions about grade separation have not been made. Is that SOP?
Q to CC: unless doing nothing is a viable option, shouldn't we do as Bill Bucy suggests: make a decision (finally) and make grant-compliance a priority? We are repeatedly told that we must pay top-tier salaries to hire and retain top-tier personnel, particularly at the senior staff level. So we do. And yet we have an unacceptable list of problems. To name just a few: the Planning & Development Department makes people crazy (and has done so for years), our housing element is not in compliance, and now we are concerned about accepting $30M in grants b/c the necessary work might not get done. This doesn't make any sense whatsoever.
Registered user
Green Acres
on Aug 29, 2023 at 4:29 pm
Registered user
on Aug 29, 2023 at 4:29 pm
Re: " unless doing nothing is a viable option" Isn't it, given that train numbers won't be increasing as thought, but instead decreasing? Not throwing good money after bad and all that. Or is there perhaps some law/directive that we have to grade separate all crossings no matter what?
Registered user
Old Palo Alto
on Aug 29, 2023 at 6:38 pm
Registered user
on Aug 29, 2023 at 6:38 pm
"is there perhaps some law/directive that we have to grade separate all crossings no matter what?"
There seems to be, in the minds of city officials and the rail committee. AFAIK they have never given the "do nothing" option serious consideration.